The bid packages have hundreds of construction teams with nearly 7,000 experts, engineers, workers, labourers and almost 3,000 pieces of construction equipment.
At bid package 5.10, construction and installation of equipment for the Long Thanh Airport passenger terminal, all reinforced concrete work for underground floors, 1F, 2F, 3F, 4F, has been completed. Compared to the plan, the construction of brick walls 1F has reached 80% in the central area and 20% in the auxiliary area. Deploying the construction of the telescopic bridge foundation. |
The production of the main steel truss for the passenger terminal steel structure has been 100% complete in the ancillary area and 61% in the central area. |
The installation of the main steel truss in the ancillary area has reached 96% and 41% in the central area. |
The processing and manufacturing of the glass wall support frame system is being carried out and is expected to be installed at the site by the end of December 2024. |
For package 4.6, construction of the runway, taxiway, and aircraft parking lot, after more than 1 year since the start of construction, the joint venture contractor has completed the foundation and foundation layers and is implementing the surface layer, with the volume reaching about 94% of the plan. |
With the current progress, the runway will be completed and put into technical operation before April 30, 2025, to celebrate the 50th anniversary of the Liberation of the South and National Reunification (April 30, 1975 - April 30, 2025), 3 months ahead of the contract schedule. |
For the construction of the second runway, Vietnam Airports Corporation (ACV) has selected a design consultant and a consulting unit and established and reviewed the basic design. At the same time, it established and reviewed the feasibility study report to adjust Component Project 3, Long Thanh Airport Construction Investment Project Phase 1. |
Workers constructing the roof of the Long Thanh Airport passenger terminal. |
Roof of the Long Thanh Airport passenger terminal. |
Long Thanh Airport air traffic control tower area. |
ACV directs contractors to speed up construction progress for other Long Thanh airport project packages, ensuring synchronous operation in September 2026. |