Su Tu Trang wellhead platform jacket and topside loaded

Nhan Dan - The PTSC Mechanical & Construction Company (PTSC M&C) under the Vietnam Oil and Gas Group, loaded the 3,500-tonne Su Tu Trang wellhead platform jacket and topside at the PTSC fabrication yard in Vung Tau city on May 14.
The Su Tu Trang wellhead platform topside.
The Su Tu Trang wellhead platform topside.

The Su Tu Trang project is a large engineering, procurement, construction and installation (EPCI) project worth US$145 million and was awarded to PTSC M&C by the Cuu Long Joint Operating Company. The PTSC M&C has set a target to complete the offshore installation this July.

On the same day, PTSC M&C signed an EPCI contract with the Lam Son Joint Operating Company worth US$113 million, for the Thang Long and Dong Do wellhead platforms.

The contract includes the engineering, procurement, construction and installation of two wellhead platforms' topsides, each weighing 1,100 tonnes, 15 kilometres of infield pipeline and 87 tonnes of Pipeline End Manifold.