Under the blazing sun with temperatures above 40 degrees Celsius, hundreds of workers and machines are busy on the construction site to maintain the progress of the project. |
Vinaconex, a contractor, said they are mobilising 100 workers on three shifts so that the final section of the bridge will be completed by June 6. |
So far, five out of eight structural connections have been done, and the remaining connections will be done in the next few days. |
Working on structural connections of the bridge. |
Many workers have to wear clothes with fans on them since the temperature on the bridge’s surface is much higher without shade and with heat radiating from machines. |
Some others use towels to cover their faces and wear sunglasses to avoid heatstroke. |
Workers are laying concrete railings. |
Despite the harsh weather, workers are making every effort to complete the project on time. |
Workers are paving the bridge’s surface with concrete asphalt. |
After the paving of concrete asphalt is done, expansion joints will be installed, one of the final stages of the project. |
According to the Hanoi transport project management board, contractors are aiming to complete all the remaining work in August so that the bridge can open to traffic on September 2. |