Expressways need fresh funding over the next five years

Viet Nam aims to complete more than 5,000 kilometres of expressways by 2030. An estimated 1.269 quadrillion VND (49 billion USD) will be needed in 2026-2030 to build new expressways, expand existing ones and complete the network.

Viet Nam aims to complete more than 5,000km of expressways by 2030, requiring an estimated 1.269 quadrillion VND in 2026-2030. (Photo: Ta Hai)
Viet Nam aims to complete more than 5,000km of expressways by 2030, requiring an estimated 1.269 quadrillion VND in 2026-2030. (Photo: Ta Hai)

The State budget and investors’ commitments are expected to cover about 423 trillion VND, leaving more than 846 trillion VND to be mobilised from non-State sources.

The Ministry of Construction has identified 29 priority expressway projects to seek investment under the public-private partnership (PPP) model, with preliminary total investment of about 922.812 trillion VND.

Given their huge capital needs and long investment and payback periods, transport infrastructure projects are under considerable pressure to raise funds and balance cash flows.

Lower interest rates do not necessarily mean easier access to capital

Alongside lower interest rates, removing barriers to credit access, diversifying funding sources and designing suitable financial mechanisms are vital for infrastructure investment projects.

PPPs offer an additional channel for raising private capital. However, such projects depend on viable financial plans, suitable loan terms, affordable capital and sound risk-sharing mechanisms.

With capital demand rising, the State Bank of Viet Nam (SBV) is taking steps to bring interest rates down. It has told credit institutions to cut deposit and lending rates, in particular by around 1.5-2 percentage points a year for production, business and priority sectors.

At a meeting with credit institutions last month, SBV Governor Pham Duc An said: “Interest rate reductions should not be applied across the board; the right beneficiaries must be selected.” He also urged banks to review existing loans to ease the cost burden on businesses.

For transport infrastructure projects, interest rates are important but do not by themselves decide access to capital. Such projects typically involve large sums, long construction periods and no stable cash flow during construction.

Banks also assess investors’ financial capacity, capital recovery plans, revenue potential, collateral and associated risks. Lower interest rates can therefore cut borrowing costs but do not guarantee credit approval if a project’s financial plan and ability to repay debt fall short of requirements.

At a conference organised by the Ministry of Construction in September to promote investment in expressway development in 2026-2030, a representative of the Public Procurement Agency under the Ministry of Finance highlighted the mismatch between loan sources and capital recovery periods.

“Project loans come mainly from commercial banks, which offer short loan terms and high interest rates, making them incompatible with transport projects’ capital recovery periods of 15 to 20 years,” the representative said.

The gap between loan maturities and capital recovery periods raises financing costs for investors, while banks must balance liquidity, credit limits and maturity risk. Addressing the funding challenge therefore requires not only reasonable borrowing costs but also lending arrangements and loan terms tailored to individual projects.

In practice, the capital requirements of transport infrastructure projects may exceed the financing capacity or credit limits of a single bank. Tran Van Tan, a VietinBank board member, said: “When a single bank finances most of the capital for a large-scale project, this creates considerable pressure on credit limits, liquidity and risk concentration.”

Syndicated lending allows several banks to co-finance a project in proportion to their capacity and credit limits, increasing the size of available loans and spreading risk.

For this to work, the participating banks must coordinate on project appraisal, disbursement, cash flow management and responses to changes in revenue.

Clear revenue risk-sharing mechanisms are essential for PPP expressway projects.
Clear revenue risk-sharing mechanisms are essential for PPP expressway projects.

Unlocking cash flow and improving the capacity to absorb capital

A 500 trillion VND credit programme for power infrastructure, transport and strategic technology projects, in which 21 commercial banks have registered to take part through the end of 2030, provides an additional funding channel for projects that are on its list and meet credit requirements.

As of August 31, 2026, outstanding loans under the programme stood at 16.91 trillion VND. Access to these loans remains subject to each bank’s assessment of financial plans, implementation schedules and debt repayment capacity.

According to economist Can Van Luc, businesses have long tended to turn straight to banks whenever they need capital. That mindset must change, he said, with businesses taking a more flexible approach and widening their fundraising options, from bond issuance and international borrowing to other channels, rather than relying on one source of funding.

The bond market and long-term investment funds can provide additional capital for projects that have been built and are in operation.

Nguyen Viet Long, Deputy General Director of Ernst & Young Viet Nam, said Viet Nam’s corporate bond market currently accounts for about 10-11% of GDP, well below that of several other economies in the region.

Long said bonds cannot fully replace bank credit because each funding channel plays a different role at different stages of a project. To draw more capital from these channels, projects must be transparent, high-quality information must be disclosed, revenue projections must be reliable, and mechanisms for adjusting service prices and managing risks must be clearly defined.

Diversifying funding must go hand in hand with building the capacity of projects and businesses to absorb capital. Even viable projects can run into trouble if procedures drag on, site clearance and handover are poorly coordinated, payment mechanisms remain unclear or operating revenues fall short of expectations. Such obstacles raise capital costs, lengthen payback periods and weigh on lending decisions.

For PPP projects, revenue risk-sharing mechanisms need to be clearly specified in financial plans and contracts. The parties involved must agree on the method for determining revenue, responsibilities for providing data, audit and settlement procedures, and deadlines for resolving discrepancies. Construction schedules should be aligned with inspection and acceptance schedules, payment arrangements and disbursement schedules.

Timely cash flow enables contractors to pay workers and suppliers, maintain equipment and rely less on costly short-term loans.

Ho Minh Hoang, Chairman of Deo Ca Group, proposed a “PPP++” approach that would involve more stakeholders across the project value chain, from state agencies, investors and contractors to suppliers of materials and equipment.

“A single financial formula cannot be applied to every project,” he said. Capital-raising plans, the allocation of responsibilities and risk-sharing arrangements should therefore reflect geography, traffic volumes, capital recovery prospects and the specific characteristics of each route.

For projects with strong prospects of recovering capital, the government should ensure sound planning, streamlined procedures and favourable conditions to attract private investment.

For routes connecting disadvantaged areas, where traffic is light but strategic significance is high, the state should consider contributing capital to make projects viable.

The participation of engineering, procurement and construction (EPC) contractors and suppliers of materials and equipment in the value chain must rest on transparent contracts, proven capacity, clear risk-sharing mechanisms and specific responsibility for quality, progress and efficient use of capital.

The target of raising about 846 trillion VND in non-state capital for expressway development in 2026-2030 requires a coordinated approach spanning monetary policy, capital markets, PPPs and project implementation.

Interest rate management must be matched by the development of long-term funding sources, syndicated lending and project bonds.

Ministries, agencies and localities need to speed up administrative procedures, meet their contractual obligations and remove obstacles, while businesses must strengthen their financial capacity, ensure transparency and improve cash flow management.

When funding arrangements are aligned with project life cycles and cash flows are secured, private capital can be channelled into infrastructure, easing pressure on credit for production and business.